When modeling to demonstrate compliance with the Prevention of Significant Deterioration (PSD) increments, it is necessary to include all PSD increment consuming sources in addition to the proposed source. All post-baseline sources emitting SO2, NO2, or PM-10 are considered to consume increment whether or not their emission rates exceed EPA's de minimus ton per year levels. It is AQD's policy that no one facility alone can consume more than 80% of a pollutants allowed increment. To determine whether or not an existing source consumes increment it is necessary to know the applicable baseline dates. There are two types of baseline dates : 1) Major Source Baseline Dates and 2) Minor Source Baseline Dates.
The Major Source Baseline Dates are fixed dates identified in the 1977 Clean Air Act for each of the 3 pollutants. Emissions associated with a modification at a major stationary source consume increment after this date.
The Minor Source Baseline Date was set by the first completed PSD application received by the Air Quality Division. Emission changes at all sources after this date affect the increment. For this reason, it is commonly referred to as the "baseline date". It is possible to expand the available increment if a post-baseline source is to reduce or eliminate the emissions of the pollutant. Minor Source Baseline Dates are established for different areas of the state called Air Quality Control Regions (AQCRs). Click here to see a figure of Michigan's AQCR's. Note that AQCR 123 has a separate area for which PM-10 has an alternate baseline date. Click here to see a figure defining this area.
Major Source Baseline Dates
|
NOX
|
TSP/PM-10
|
SO2
|
|
February 8, 1988
|
January 6, 1975
|
January 6, 1975
|
Minor Source Baseline Dates
Minor Source Baseline Dates are revised as of 06.12.03.
|
AQCR #
|
NOX
|
TSP/PM-10
|
SO2
|
|
122
|
March 28, 1988
PN 943-87
ADA COGENERATION
Ada
|
January 31, 1980
PN 541-79
GRAND HAVEN BOARD OF LIGHT & POWER
Grand Haven
|
January 31, 1980
PN 541-79
GRAND HAVEN BOARD OF LIGHT & POWER
Grand Haven
|
|
123
|
December 28, 1989
PN 1144-89
OAKLAND COUNTY INCINERATOR
Auburn Hills
|
June 24, 1978
PN EPA-5-A-79-10
MARBLEHEAD LIME
Detroit
|
June 24, 1978
PN EPA-5-A-79-10
MARBLEHEAD LIME
Detroit
|
|
123*
|
July 21, 1999
PN 269-99
DETROIT EDISON RIVER ROUGE
River Rouge
|
|
124
|
January 19, 1995
PN 28-95 & 29-95
NORTH STAR STEEL / BHP
Dundee
|
February 1, 1978
PN EPA-5-A-79-5
NORTH STAR STEEL
Monroe
|
February 1, 1978
PN EPA-5-A-79-5
NORTH STAR STEEL
Monroe
|
|
125
|
March 4, 1988
PN 748-87
MICHIGAN STATE UNIVERSITY
East Lansing
|
April 24, 1979
PN EPA-5-A-79-20
GM, HYDRAMATIC DIV.
Three Rivers
|
April 2, 1979
PN EPA-5-A-79-16
UPJOHN CORPORATION
Kalamazoo
|
|
126
|
May 13, 1988
PN 519-87A
TONDU ENERGY SYSTEMS
Filer City
|
February 8, 1980
PN 6-80
MEAD PAPER CO.
Escanaba
|
February 8, 1980
PN 6-80
MEAD PAPER CO.
Escanaba
|
|
82
|
December 27, 1994
PN 489-94
NORTH STAR STEEL
Benton Harbor
|
December 27, 1994
PN 489-94
NORTH STAR STEEL
Benton Harbor
|
December 27, 1994
PN 489-94
NORTH STAR STEEL
Benton Harbor
|
*Note that there is a separate area within AQCR 123 for which PM-10 has an alternate baseline date. Click here to see a figure defining this area.
|