|
|  |
Printer Friendly
Text Version Email Page
| DEQ Project Creates Prime Redevelopment Possibilities in Downtown Detroit
Contact:
Patricia Thornton 313-456-4669
Agency:
Environmental Quality
|
|
Urban
redevelopment plays a large role in the DEQ’s efforts to provide for a healthy
environment, and a healthy economy. We partner with local communities to
restore properties to their full potential and provide for new growth
opportunities, while at the same time ensuring that these projects are
protective of the local environment and public health.
One
project that certainly exemplifies this commitment is the removal of the former
Statler Hilton Hotel in
Detroit. The plan to
demolish the hotel was a controversial one for many people in the area due to
the historic qualities of the building, however, once the decision was made to
move forward with the project in 2005, the DEQ’s role was to ensure that it was
done safely.
The former Statler Hilton
Hotel site is located on the west side of Washington Blvd., between Bagley and
Park Streets, and is in the
Grand Circus Park District.
The building was a eighteen story structure of 515,000 square feet and 800
guestrooms that was built in 1914 as part of the Statler chain, and acquired by
the Hilton Hotel chain in 1954. It was closed in 1975 and has been unoccupied
since.
|
|

|

|
|
Front (left) and rear (right) views of the former Detroit Statler Hilton. Note Comerica Park in the upper right during beginning stages of demolition.
|
|
An effort to restore use of the
hotel began in 1999, when the DEQ allocated
Clean Michigan Initiative (CMI) funds
for site assessment in preparation for rehabilitation.
Activities commenced in October of 2001 to remove asbestos containing materials
and debris, lead based paint material and debris, universal wastes, and
miscellaneous hazardous and non-hazardous materials found throughout the
building, and were completed in May of 2002.
When private developers could not economically renovate or redevelop the
building, the City of Detroit again
called on the MDEQ assistance as the property had then become a serious
impediment to redevelopment of adjacent areas.
Thousands of tons (approximately 130,000) of non-hazardous building debris have
been removed and disposed, and risk abatement measures taken for asbestos, lead,
and polychlorinated biphenyls (PCB) contamination.
|
Demolition Site Work
|
In February
of 2004 the State of Michigan developed bid specifications to demolish, remove,
and dispose of the building and debris generated from the demolition. The former
Statler Hotel building stood 210 feet tall overall and sat four feet from the
Detroit People Mover
Track on the Park Street side of the building.
As part of the site preparation, protection of all adjacent structures, including the Detroit People Mover track (DPM) and adjacent buildings at 1501 Washington Blvd. and 139 Bagley Avenue, was of extreme importance.
In order to protect the DPM track, the Park street side of the Statler building was covered in 40,000 square feet of fencing and debris netting attached to scaffolding, which provided a safety net during demolition of the building. In addition, all demolition work performed on the Park and Bagley sides of the building had to be performed from 12:00 AM to 5:00 am, so that the People Mover could remain in full service to the City of Detroit.
To prevent any damage to the DPM railway, vibration
monitoring was also required by the DPM for the duration of the demolition.
Vibrations were monitored by a series of geophones attached to the DPM track.
The geophones were triggered to set off alarms any time high peak vibrations
caused by impacts from falling debris occurred.

Cutting Steel Beams on 9th Floor
The proximity of the track and other buildings resulted in hand demolition of the building. This required the use of torch cutters, skid steer loaders, mini excavators and breakers, and an ultra high reach excavator with hydraulic extendable booms with three stages and hydraulic shears (reaching to 140 feet), to execute the demolition.
|
|

Two Views of the interior of the Statler Hilton


Demolition

|
|
PCB Removal
During the demolition and basement
slab removal phases, accumulated contaminated water was treated with carbon for
PCB removal. The sources of the PCBs were
transformer carcasses and capacitors which had been scavenged by urban dwellers
and left to leak oils onto the concrete of the basement floor.
Approximately 100 tons of concrete and 525 tons of the soil contaminated with
PCBs were removed as the final stage of remediation before backfilling could be
completed on the building site.
Air Monitoring
In order to provide the Air Quality Division
data that the demolition and asbestos abatement activities would not endanger
the surrounding community, a total of six air monitoring stations, including one
weather recording station, were installed around the outside perimeter of
the site. These stations continuously recorded and measured particulate
values, and asbestos and lead levels surrounding the site during the entire time of
site work.
|
|

PCB Excavation

Air monitoring
|
| Site work began on December 13, 2004 with removal, treatment, and discharge of PCB contaminated water from the basement and subbasement to the storm sewer. Site work continued with abatement of all concealed remaining asbestos containing materials and manual demolition of all 18 floors on the northern, eastern, northwestern, and central areas of the building. The actual building demolition was completed October 27, 2005. |
|
Scaffolding, fencing and debris netting were used to protect the People Mover.
|
|
The now vacant lot is triangular in shape and contains approximately 32,000 square feet. The parcel has access to the Detroit People Mover and is within a short walk from the Comerica Park and Ford Field. The Detroit Economic Growth Corporation will advertise for proposals to redevelop
approximately one-acre property on Grand Circus Park.
The DEQ was proud to be a part of this project that
was done safely, and will provide Detroit with the opportunity to grow.
|
|
A new sky line appears (photo on the left) and DEQStaff involved in the project from left to right: Southeast MI District Office Supervisor, Oladipo Oyinsan, Project Manager, Patricia Thornton, and DLZ's Engineer on site, Tom Hutchinson.
|
|
|