The relocation of an exisiting ski lift requires that an application and relevent exhibits be submitted to the department. Where plans/drawings are already on file with the department, (sections unaffected by the relocation), provide a list of those for reference. Upon review and approval, a Phase One permit will be issued allowing foundations to be poured.
An inspection and additional exhibits must be submitted to the department to advance to Phase Two of the permit process allowing the machinery construction.
A final construction permit will be issued and load testing and final inspections scheduled upon submittal of exhibits required for Phase Three of the permit process.