WHAT: Public information meeting for residents to learn more about the reconstruction of M-52 between Morrice Road and M-21 in Owosso. There will be a short presentation followed by an opportunity to ask questions of Michigan Department of Transportation (MDOT) staff.
WHO: MDOT staff
City of Owosso officials
General public
WHEN: Thursday, Oct. 22, 2009
5 - 7 p.m.
WHERE: Baker College Welcome Center
South M-52
Owosso
BACKGROUND: Work on M-52 involves roadway reconstruction, new curb and gutter, storm sewer and water main improvements, railroad crossing reconstruction, traffic signal upgrades, and sidewalk improvements. Once the project is complete, M-52 will be restriped from its current four-lane configuration to a three-lane roadway with a center-turn lane.
Work will begin first on the railroad reconstruction, which requires a full closure of M-52. Once this work is complete prior to the Memorial Day holiday, the roadway reconstruction portion will begin. This work will require one lane of northbound traffic on M-52 to be maintained through the work zone, with southbound traffic detoured.
All work is expected to be completed by November 2010.