Q 4. If I have an increased quantity of an existing bid item and an extra, can I submit them both on the same contract modification?
|
|
|
|
Answer:
|
|
Yes you can, but you probably do not want to if the extras require further review (FHWA, State Administrative Board, State Transportation Commission). If you submit the quantity increase by itself, it can be approved at the TSC level. If they are combined, nothing can be until the extra is approved.
|
 |