Contact:
James Lake, MDOT Office of Communications, 906-786-1830, ext. 323
Agency:
Transportation
COUNTY: Dickinson
HIGHWAY: M-95 (Carpenter Avenue)
CLOSEST CITY: Iron Mountain
ESTIMATED STARTING DATE: Monday, Oct. 12, 2009
ESTIMATED COMPLETION DATE: Friday, Nov. 6, 2009
PROJECT: The Michigan Department of Transportation (MDOT) will be upgrading traffic signals at the intersections of M-95 with A Street and B Street in Iron Mountain. The project includes replacement of the signal heads and poles, as well as upgrades to adjacent sidewalk ramps.
TRAFFIC RESTRICTIONS: This project will require intermittent lane closures, primarily with traffic shifts, but occasionally with flag control.
For up-to-date information on this project, go to the list of statewide lane closures at: www.michigan.gov/drive.
MDOT: Working to improve our state roads and bridges.