Summer 2006 |
|
|
| |
|
--- |
Decision made to split the project into two studies: the Blue Water Bridge Plaza Reconstruction Study and the I-94/I-69 Corridor Study |
| |
Fall 2006 |
|
|
| |
|
--- |
"Likely" plaza alternative identified |
| |
Winter 2006-07 |
|
|
| |
|
--- |
Local/state planning begins |
| |
|
|
|
| |
Summer 2007 |
|
|
| |
|
--- |
Decision made to recombine the Corridor study and Plaza study into one Draft Environmental Impact Statement |
| |
Fall 2007- |
|
|
| |
|
---
--- |
Release of Draft Environmental Impact Statement
Public hearing on Draft Environmental Impact Statement
|
| |
Summer 2008 |
|
|
| |
|
--- |
MDOT releases preliminary Recommended Alternative and continues preparing reponses to DEIS comments |
|
Winter 2008/09 |
|
|
| |
|
--- |
Projected Final Environmental Impact Statement Release
|
| |
|
--- |
Federal approval of plaza plan |
| |
Spring 2009 |
|
|
| |
|
--- |
Design and right-of-way acquisition begins |
| |
2011-2013 |
|
|
| |
|
--- |
I-94/I-69 corridor construction begins |
| |
2012-2015 |
|
|
| |
|
--- |
Property purchase complete |
| |
|
--- |
Plaza construction begins |
| |
|
|
|
| |
|
|
|