Study schedule

Milestones for the Blue Water Bridge Plaza and Corridor project are listed below, with projected dates.

  Summer  2006    
    --- Decision made to split the project into two studies: the Blue Water Bridge Plaza Reconstruction Study and the I-94/I-69 Corridor Study
 
Fall 2006
   
    --- "Likely" plaza alternative identified
 
Winter 2006-07
   
    --- Local/state planning begins
       
  Summer 2007     
    --- Decision made to recombine the Corridor study and Plaza study into one Draft Environmental Impact Statement
 
Fall 2007-
   
    ---
---

Release of Draft Environmental Impact Statement
Public hearing on Draft Environmental Impact Statement

 
Summer 2008
   
    --- MDOT releases preliminary Recommended Alternative and continues preparing reponses to DEIS comments

Winter 2008/09
   
    ---

Projected Final Environmental Impact Statement Release

    ---  Federal approval of plaza plan
 
Spring 2009
   
    --- Design and right-of-way acquisition begins
 
2011-2013
   
    --- I-94/I-69 corridor construction begins
 
2012-2015
   
    ---  Property purchase complete
    ---  Plaza construction begins
       
       


Related Documents
Blue Water Bridge Plaza & I-94/I-69 Corridor Project Schedule - 17769 bytes PDF icon