The US-131 Improvement Study began in February 2000. In January 2001, at the request of the local communities, the Michigan Department of Transportation (MDOT) extended the US-131 Improvement Study five miles north to approximately one mile north of Lovers Lane. In addition, two new non-freeway alternatives were added by MDOT in 2003.
Figure 2 shows where we are in the study schedule. The Draft Environmental Impact Statement (DEIS) has been completed. The next step is the Public Hearing, followed by determining a preferred alternative in the Fall of 2005, and completing the Final Environmental Impact Statement in 2006.
The major milestones & anticipated schedule are:
Spring 2005 Draft Environmental Impact Statement (DEIS) Distributed
Spring 2005 Public Hearing
Fall 2005 Determine & Review Recommended Alternative
Summer 2006 Complete Final Environmental Impact Statement (FEIS)
Summer 2006 Obtain Record of Decision
Summer 2006 Study Closeout
Following Environmental Clearance (Record of Decision), Preliminary Engineering (Design), then Right-Of-Way Acquisition and Construction may follow at a future date.