Nighttime I-94 resurfacing project starts Oct. 1 in Jackson County

Contact: Kari Arend, MDOT Office of Communications, 517-750-0406
Agency: Transportation

COUNTY:
Jackson

ROADWAY:
I-94

CLOSEST CITY:
Jackson

START DATE:
Sunday, Oct. 1, 2017

ESTIMATED COMPLETION DATE:
End of October 2017

PROJECT:
Starting next week, a project will begin to resurface I-94 between M-60 and Sargent Road. The project is expected to last approximately four weeks.

Project map: https://goo.gl/8Ct4Pi

TRAFFIC IMPACTS:
During construction, there will be nighttime, single-lane closures on I-94 between 8 p.m. and 6 a.m. each night Monday through Thursday, and between 9 p.m. and 6 a.m. on Sundays. No work will take place on Fridays or Saturdays.