96 Fix bridge closure update for April 18

Contact: Diane Cross, MDOT Office of Communications,
 crossd2@michigan.gov
248-752-0336
Agency: Transportation

As part of the 96 Fix project in Livonia, the following is a current list of bridges over I-96 that are open, closed, or scheduled to be closed soon:

Bridge #

Road name

Closure Type

Status

Estimated reopening

1

Schoolcraft Road

Part-width

Open

 

2

Newburgh Road westbound U-turn

Full closure

Closed

October

3

Newburgh Road

Part-width

Closing early May

Mid-July

4

Newburgh Road eastbound U-turn

Full closure

Closed

Mid-May

5

Levan Road westbound U-turn

Full closure

Closed

Late May

6

Levan Road

Part-width

Open

 

7

Levan Road eastbound U-turn

Full closure

Closing late April

Late May

8

Yale Street

Full closure

Open

 

9

Wayne Road

Full closure

Closed

Late May

10

Stark Road

Full closure

Open

 

11

Farmington Road westbound U-turn

Full closure

Closed

Late April

12

Farmington Road

Part Width

Open

 

13

Farmington Road eastbound U-turn

Full closure

Closed

Late April

14

Brookfield Street

Full closure

Closing late April

Late May

15

Berwick Street

Full closure

Open

 

16

Merriman Road westbound U-turn

Full closure

Open

 

17

Merriman Road

Full closure

Open

 

18

Merriman Road eastbound U-turn

Full closure

Open

 

19

Warner Court

Full closure

Closed

Mid-June

20

Melvin Street

Full closure

Open

 

21

Middlebelt Road westbound U-turn

Full closure

Closed

Late-May

22

Middlebelt Road

Part-width

Open

 

23

Middlebelt Road eastbound U-turn

Full closure

Closed

Mid-May

24

Racetrack

Full closure

Open

 

25

Cardwell Street

Full closure

Open

 

26

Inkster Road westbound U-turn

Full closure

Closed

Mid-May

27

Inkster Road

Full closure

Open

 

28

Inkster Road eastbound U-turn

Full closure

Closed

Mid-May

29

Breakfast Drive

Full closure

Open

 

30

Berwyn Avenue

Full closure

Closed

Mid-May

31

Beech Daly Road westbound U-turn

Full closure

Open

 

32

Beech Daly Road

Part-width

Open

 

33

Beech Daly Road eastbound U-turn

Full closure

Open

 

34

Garfield

Full closure

Closed

Mid-May

35

Fenton

Full closure

Open

 

36

US-24 southbound service drive

Part-width

Open

 

37

US-24 northbound service drive

Full closure

Closed

Mid-May

 

TRAFFIC IMPACT:
Motorists will be detoured to the next available bridge.

PROJECT DETAILS:
The 96 Fix project between Newburgh and Telegraph roads involves reconstructing the freeway, repairing 37 overpasses and upgrading utilities. I-96 will be closed throughout the project, and is expected to reopen in October.

For more information on this $148 million investment, go to the project website at www.96fix.com. Follow project updates on www.facebook.com/96fix and www.twitter.com/96fix.