MPSC Establishes Procedures for Its Staff to Use in Working with the MDEQ on Proposed New Coal-Fired Electric Plants

Contact:  Judy Palnau (517) 241-3323


April 30, 2009

The Michigan Public Service Commission (MPSC) today issued an order that establishes procedures for the MPSC staff to follow as it works with the Michigan Department of Environmental Quality (DEQ) on proposed new coal-fired electric generating plants.

On Feb. 3, Governor Jennifer M. Granholm issued an executive directive (ED 2009-02) that directed the DEQ, before issuing a permit for the construction of a new coal-fired electricity generating plant, to determine whether there is a feasible and prudent alternative consistent with public health and safety and environmental concerns.

On April 1, the MPSC entered into a Memorandum of Understanding (MOU) with the DEQ that clarified each participant's role and responsibility regarding a review that will look at electric generation alternatives and providing technical assistance to the DEQ. 

The DEQ is charged with issuing permits in response to applications filed seeking authority to construct a new coal-fired electricity generating plant.

The MPSC has two tasks, pursuant to the MOU:

·         Providing technical assistance to the DEQ on all matters related to the need for electric generation in the state, as it relates to the analysis that looks at alternatives to coal-fired generation.

·         Reviewing the alternatives analysis to assess whether energy efficiency, renewable energy, or other alternatives meet future electricity needs.

The DEQ is responsible for reviewing the alternatives analysis to assess the affect of the plants and alternatives on human health and the environment.

Today's order directs the MPSC staff to perform the following activities:

A.   As required, the Regulatory Affairs Division shall open separate dockets for each investigation and shall manage the files and information gathered as part of the process.  Although the investigation process established by this order will not be conducted as a contested case proceeding, the information in the dockets opened for each investigation shall be available to the general public pursuant to the Commission's e-file system.

B.   The Electric Reliability Division shall assume the lead role in all technical investigations required by the MOU.  The Electric Reliability Division shall contact existing DEQ permit applicants within 3 business days of the issuance of this order to inform each applicant of the review process established by the Commission.  Subsequently, the Electric Reliability Division shall contact new DEQ permit applicants within 3 business days of discovery of the filing of a permit application to inform the new applicants of the review process established by the Commission.

C.   Each permit applicant shall submit an electric generation alternatives analysis (EGAA) to the Commission.  Each EGAA shall include all of the following information:

·               Consideration of alternatives that would reduce emissions of the criteria pollutants [nitrogen oxides (NOx), carbon monoxide (CO), volatile organic compounds (VOCs), particulate matter (PM), particulate matter less than 10 microns (PM10), sulfur dioxide (SO2), lead (Pb), other hazardous air pollutants, including mercury (Hg), and carbon dioxide (CO2)] from the proposed facility;

·               The analysis should address cost, reliability, availability, and technical feasibility of the alternatives examined.  Cost should be presented in a manner that facilitates a comparative analysis (i.e., dollars per megawatt-hour (MWh) for each option);

·               Reduced generating capacity - description of future energy requirements and the adequacy of existing supplies.  Provide the basis for the proposed design and address whether smaller boilers, a reduced number of boilers, or no new boilers are viable options in light of the other alternatives addressed;

·              Improved energy efficiency at existing units - description of the energy efficiency measures available at existing units owned or controlled by the applicant to fully or partially offset the emissions from the proposed facility;

·              Potential supply resources - description of the technologies considered for new generation including the consideration of renewable energy sources, clean fuels (primary fuel and fuel alternatives), and lower emitting technologies.

o        Renewable energy sources (i.e., wood, other biomass, etc.)

o        Clean fuels (i.e., low sulfur coal, etc.)

o        Lower emitting technologies

§         Natural gas

§         Wind

§         Solar

§         Hydroelectric

§         Nuclear

§         Wave Energy

§         Geothermal

§         Combined Heat and Power

§         Other innovative fuel combustion techniques

§         Cleaner technologies

§         Sequestering activities

·               Demand side management/reduction - description of load management, energy efficiency, and distributed generation as a means of affecting forecasted load requirements;

·               Combinations of these alternatives raised in public comments received during the DEQ public comment period.

D.   The Staff and the applicant shall meet approximately 7 days after submittal of the Electric Generation Alternatives Analysis with weekly update meetings thereafter, as necessary.

E.   After the filing of an EGAA with the Commission, the public shall have 30 days to comment on the filing.

F.   After conclusion of the public comment period, the Staff shall within 60 days review the filed comments, continue review of the EGAA filing, perform any required analysis, and develop and prepare a report to the DEQ.  In developing this report, the Staff shall give consideration to all reasonable and relevant filed comments.  The applicant shall provide the Staff with any information necessary to assist the Staff in the evaluation and review of the EGAA filing.  

G.   In accordance with the MOU, the Staff will review the alternatives analysis for the proposed coal-fired electricity generating plants to assess whether energy efficiency, renewable energy, or other alternatives meet future electricity needs.

The MPSC is an agency within the Department of Energy, Labor & Economic Growth.

Case No. U15958

 

 

Michigan Business One Stop
Link to Department and Agencies Web Site Index
Link to Statewide Online Services Index
Link to Statewide Web-based Surveys
Link to RSS feeds available on this site
Related Content
 •  MPSC: Gas Choice Participation at All-Time High in Michigan
 •  CORRECTION: MPSC: Home Heating Credits Now Being Processed
 •  MPSC Approves Settlement Agreement Approving Power Purchase Agreement between Detroit Edison Company and Blue Water Renewables for Unique Landfill Gas Site
 •  MPSC Directs Michigan Consolidated Gas Company to Refund $25.8 Million to Natural Gas Customers
 •  MPSC Approves Settlement Agreement Authorizing Presque Isle Electric & Gas Co-op to Implement 2011 Power Supply Cost Recovery Factor
 •  MPSC Approves Settlement Agreement Authorizing Great Lakes Energy Cooperative to Implement 2011 Power Supply Cost Recovery Factor
 •  MPSC Approves Settlement Agreement Reconciling Consumers Energy Company's Enhanced Security Costs, Customers to See $1.4 Million Refund
 •  MPSC Reconciles The Detroit Edison Company's Regulatory Asset Recovery Surcharge
 •  MPSC Designates Jackson 2-1-1 Call Center, Inc. as 2-1-1 Answering Point for 22 Exchanges in Genesee and Shiawassee Counties
 •  MPSC Approves Settlement Agreement Authorizing SEMCO Energy Gas Company to Increase Rates
 •  MPSC Approves Settlement Agreement Reconciling Northern States Power Company's 2009 Power Supply Costs
 •  MPSC Approves Settlement Agreements Authorizing the 2011 PSCR Factors for Three Electric Cooperatives
 •  Michigan's Net Metering Program Gets an "A"
 •  MPSC: Michigan Electric Utilities on Track to Meet Renewable Energy Standard
 •  MPSC to Hold Public Hearing on Proposed Mergers and Acquisition Rules
 •  MPSC Directs Consumers Energy Company to Refund $10.7 Million to Natural Gas Customers
 •  MPSC Requires Electric Utilities to File Assessments of Their Ability to Meet Peak Summer Demand
 •  MPSC Directs Detroit Edison to Refund $26.8 Million to Its Electric Customers
 •  MPSC Approves Solar Energy Contracts for Consumers Energy Company
 •  MPSC Approves Settlement Agreement Reconciling Wisconsin Public Service Corporation's 2009 Power Supply Costs

Michigan.gov Home | LARA Home | MPSC Home | State Web Sites
Accessibility Policy | Link Policy | Privacy Policy | Security Policy | Michigan News | Michigan.gov Survey

Copyright © 2001-2012 State of Michigan