System News Update

  • Message from the Director

    To the citizens of Michigan and MPSCS users:

    Michigan’s Public Safety Communications System is undertaking a 10-year project to replace critical equipment that is integral to the public safety communications network. Each year, funds will be allocated to perform necessary updates and repairs to aging electronic equipment at towers sites across the state. This project is critical t ... READ MORE

Progress of the Project

  • MPSCS Lifecycle Remediation Project Schedule
    Task Name Target Completion
    Global Design Plan (GDP) Closure Complete
    MCC 7500 GPIOM Replacements with VPMs Complete
    Phase 1 ASR-DC Equipment (76 Sites) Complete
    Phase 1 Nokia Microwave Equipment (43 Hops) Complete
    Phase 1 Technical Training (30 Sessions) Complete
    Phase 2 Technical Training Complete
    Phase 2 ASR-DC Equipment (42 Sites)  
         Detailed Design Plan (DDP) Complete
         Equipment Staging, and Shipment Complete
         Method of Procedure (MOP) Development Complete
         Notice to proceed with implementation Complete
         Implementation Complete
         Acceptance Testing Complete
         ATP Document (Punchlist) Complete
         Final Documentation Complete
     READ MORE