M-57 culvert replacement at Bradley Drain in Gratiot County starts April 15

Contact: Jocelyn Hall, MDOT Office of Communications, HallJ20@Michigan.gov, 989-245-7117
Agency: Transportation

COUNTY:
Gratiot

HIGHWAY:
M-57

CLOSEST CITIES:
Pompeii
Perrinton

ESTIMATED DATE:            
Monday, April 15, 2019

ESTIMATED COMPLETION DATE:      
November 2019

PROJECT:
The Michigan Department of Transportation (MDOT) will invest $1.2 million to replace the culvert at Bradley Drain on M-57.

Project map: http://bit.ly/2P0xEVw

TRAFFIC RESTRICTIONS:
April 15 – June 1 motorists can expect single-lane closures maintained with flag control as crews stage the area and build a temporary bridge. Beginning approximately June 11 a single-lane temporary bridge will maintain both directions of traffic.

SAFETY IMPROVEMENTS:
This project will replace the existing structure, ensuring proper drainage and water flow of the Bradley Drain under M-57.