M-13 resurfacing through Pinconning starts July 15

Contact: Jocelyn Hall, MDOT Office of Communications, 989-245-7117
Agency: Transportation

COUNTY:
Bay                              

HIGHWAY:                                   
M-13

CLOSEST CITY:                 
Pinconning                                   

ESTIMATED START DATE:            
Monday, July 15, 2019

ESTIMATED COMPLETION DATE:      
November 2019

PROJECT:                          
The Michigan Department of Transportation (MDOT) will invest $7.2 million to resurface 3.4 miles of M-13 from North Street in the city of Pinconning to the Arenac County line. Work includes resurfacing the roadway, joint repairs, concrete curb and gutter, sidewalk, and intersection improvements.  

Project map: http://bit.ly/309qXEV

TRAFFIC RESTRICTIONS:                     
One lane will remain open in each direction during paving. Intersection work at M-13/Cody Estey Road will require a detour of Cody Estey Road via Water Street, Pinconning Road, and Mackinaw Road.

SAFETY BENEFITS:
This work will improve the pavement surface of M-13, extending the life of the roadway.