Eastbound I-94 bridge work and ramp closure at M-140 starts Monday

Contact: Nick Schirripa, MDOT Office of Communications, SchirripaN@Michigan.gov, 269-208-7829
Agency: Transportation

COUNTY:
Berrien

HIGHWAY:
I-94

CLOSEST CITY:
Watervliet

START DATE:
Monday, Sept. 9, 2019

ESTIMATED END DATE:
Friday, Oct. 25, 2019

PROJECT:
The Michigan Department of Transportation will be working on the eastbound I-94 bridge over M-140. This $340,000 investment includes joint replacement, deck sealing, railing replacement, and approach work.

For project details and a map, visit Mi Drive.

SAFETY BENEFITS:
This project will extend the service life of the bridge and improve safety.

TRAFFIC RESTRICTIONS:
Two eastbound lanes will be open on I-94 during construction.

The eastbound I-94 ramp to M-140 at Exit 41 will be closed throughout construction. Traffic will be detoured from eastbound I-94 to Exit 39 Friday Road/Church Street, north to Red Arrow Highway, then east to M-140.