I-69 Project, Calhoun and Eaton Counties

Start: September 2020     End: November 2023
 
Poster for Rebuilding Michigan Project Profiles - I-69 Calhoun/Eaton
 
What Is Being Done?


Phase 1: 2021

  • Rebuild northbound and southbound I-69 from Ainger Road in Olivet to Island Highway in Olivet, Eaton County.
  • Rebuild interchange ramps at Cochran Road and M-50.
  • Maintenance on the J Drive North, N Drive North, Garfield Road, Baseline Highway, Butterfield Highway, and Ainger Road bridges over I-69.

Phase 2: 2022

  • Rebuild northbound I-69 from I-94 to north of Ainger Road. 
  • Rebuild interchange ramps within the project limits.
  • Rebuild a portion of the I-94/I-69 interchange.
  • Replace the 15 Mile Road bridge over I-94.

Phase 3: 2023

  • Rebuild southbound I-69 from I-94 to north of Ainger Road.
  • Rebuild interchange ramps within the project limits.
  • Rebuild remaining portion of the I-94/I-69 interchange.
  • Preventive maintenance on 26 bridges along the I-69 corridor will take place over all three phases of the project.
How Traffic Will Be Affected:

 

  • During work, one lane will be open in each direction on I-69.
  • Interchange ramps will remain open except for short durations for rebuilding.
  • The 15 Mile Road bridge over I-94 will be closed and detoured while it is being rebuilt. 
  • Bridge closures will be required during preventive maintenance work. 

 

Additional Info:


I-69 Corridor Public Meeting Presentation PDF icon
Contract has been awarded to Michigan Paving and Materials.

Contact Us:


Lansing Transportation Service Center at 517-335-3754
Marshall Transportation Service Center at 269-789-0560
www.Michigan.gov/Drive
www.twitter.com/MDOT_Southwest
www.facebook.com/MichiganDOT
Subscribe to the I-69 rebuilding project e-mail list  E-mail Alert via Gov Delivery