I-69 Reconstruction, Calhoun & Eaton Counties

Start: September 2020     End: November 2023
 
What Is Being Done?


Phase 1: 2021

  • Rebuild northbound and southbound I-69 from Ainger Road in Olivet to Island Highway in Olivet, Eaton County.
  • Rebuild interchange ramps at Cochran Road and M-50.
  • Maintenance of the J Drive North, N Drive North, Garfield Road, Baseline Highway, Butterfield Highway, and Ainger Road bridges over I-69.

Phase 2: 2022

  • Rebuild northbound I-69 from I-94 to north of Ainger Road
  • Rebuild interchange ramps within the project limits
  • Rebuild a portion of the I-94/I-69 interchange
  • Replace the 15 Mile Bridge over I-94

Phase 3: 2023

  • Rebuild southbound I-69 from I-94 to north of Ainger Road
  • Rebuild interchange ramps within the project limits
  • Rebuild remaining portion of the I-94/I-69 interchange
  • Bridge preventative maintenance on 26 bridges along the I-69 corridor will take place over all 3 phases of the project
How Traffic Will Be Affected:

 

  • During work, one lane will be open in each direction on I-69
  • Interchange ramps will remain open except for short durations for reconstruction
  • The 15 Mile Bridge over I-94 will be closed and detoured while it is being rebuilt
  • During bridge preventative maintenance work bridge closures will be required

 

Additional Info:


I-69 Corridor Public Meeting Presentation PDF icon
Contract has been awarded to Michigan Paving and Materials.

Contact Us:


Lansing Transportation Service Center at 517-335-3754
Marshall Transportation Service Center at 269-789-0560