I-75 lane and ramp closures begin Monday, March 8, in Oakland County
Fast facts:
- Northbound I-75 will have lane closures from Big Beaver to Wattles roads.
- All ramps at the I-75/Big Beaver Road interchange will close for two weeks.
March 4, 2021 -- Weather permitting, lane and ramp closures will begin at 7 a.m. Monday, March 8, on I-75 for punch list items and sound wall construction in the city of Troy. Beginning at 7 a.m., the following restrictions will be in place:
- Only the left lane will be open on northbound I-75 at Big Beaver Road as crews work on repairing a drainage connection. The double-lane closures are expected to remain in place until sunset on March 15.
- Pavement work will require closing all ramps at the I-75/Big Beaver Road interchange for two weeks. Northbound ramp traffic will be detoured to the Crooks Road/Corporate Drive interchange while southbound ramp traffic will be directed to Rochester Road.
- Northbound I-75 will have two lanes open near Wattles Road as crews build a new sound wall. The lane closures are expected to remain in place until mid-April.
Follow I-75 modernization progress on the web at www.Modernize75.com, or follow on Facebook at www.facebook.com/Modernize75 or on Twitter at www.twitter.com/Modernize75.