Work resumes on I-69 and three bridges in Coldwater
COUNTY:
Branch
HIGHWAY:
I-69
CLOSEST
Coldwater
START DATE:
Monday, April 12, 2021
ESTIMATED END DATE:
Friday, Aug. 27, 2021
PROJECT:
The Michigan Department of Transportation (MDOT) is completing work on 12 miles of I-69 and three bridges (Fenn Road, State Road and Newton Road) between Girard Road and Otis Road.
Started in 2020, this $7.7 million investment includes pavement and joint repairs, resurfacing, crack sealing, and drainage improvements on I-69 between Otis Road and Girard Road. The State Road and Newton Road bridges will be painted this year.
For more information and a map, visit Mi Drive.
SAFETY BENEFITS:
This project will improve ride quality and provide a longer lasting pavement on I-69. It will also extend the life of the Fenn Road, State Road, and Newton Road bridges.
TRAFFIC RESTRICTIONS:
One lane of I-69 will remain open in each direction.