US-41 Chassell culvert replacement starts May 17

COUNTY:
Houghton

HIGHWAY:
US-41

CLOSEST TOWN:
Chassell

ESTIMATED STARTING DATE:
Monday, May 17, 2021

ESTIMATED COMPLETION DATE:
Friday, Sept. 10, 2021

PROJECT:
The Michigan Department of Transportation (MDOT) will invest $873,000 to replace a culvert on US-41 over an unnamed stream just north of First Street/Lakeshore Drive in Chassell, Houghton County. The project includes rebuilding asphalt roadway, scour countermeasures and pavement markings.

The project map is available on Mi Drive.

TRAFFIC RESTRICTIONS: 
The work will require shoulder closures starting May 17. Beginning June 7, one lane will be open in each direction via temporary traffic signals. A 12-foot width restriction will be in place for the duration of this project.

SAFETY BENEFITS:
The project will provide a long-term replacement for a culvert and roadway damaged in the June 2018 Father's Day Flood.