Skip to main content

Bridge beam setting requires closing a portion of I-94 this weekend in Detroit

Fast facts:
- MDOT is replacing the Burns Street overpass above I-94.
- Bridge beam setting requires closing I-94 between I-75 and M-3 (Gratiot Avenue) starting Friday night.
- This section of I-94 is expected to reopen by 5 a.m. Monday, Nov. 22.


November 17, 2021 - Weather permitting, Michigan Department of Transportation (MDOT) contract crews will be setting bridge beams at the Burns Street overpass above I-94 in Detroit this weekend. This work will require closing both directions of I-94 between I-75 and M-3 starting at 9 p.m. Friday, Nov. 19. This section of I-94 is expected to reopen by 5 a.m. Monday, Nov. 22.

During this closure, westbound I-94 traffic will be detoured via southbound M-3 (Gratiot Avenue), the westbound Gratiot Connector, and northbound I-75 back to westbound I-94.

All entrance ramps to westbound I-94 will be closed by 9 p.m. from Chalmers to Mt. Elliott streets and will reopen by 5 a.m. Monday.

Eastbound I-94 traffic will be detoured via southbound I-75, the eastbound Gratiot Connector, northbound M-3, and eastbound M-102 back to eastbound I-94. All entrance ramps to eastbound I-94 will be closed by 9 p.m. from I-96 to Gratiot Avenue and will reopen by 5 a.m. Monday.

The new Burns Street bridge will replace the current structure built in 1954.  

Follow the I-94 modernization project on the web at https://I94Detroit.org or follow on Facebook at www.facebook.com/I94Detroit or on Twitter at www.twitter.com/I94Detroit.   

Media Contact:

Author: