The web Browser you are currently using is unsupported, and some features of this site may not work as intended. Please update to a modern browser such as Chrome, Firefox or Edge to experience all features Michigan.gov has to offer.
I-94 expansion progresses in Kalamazoo as work begins shifting to westbound lanes
April 04, 2022
This is the second year of work on the two-year project to widen 2.7 miles of I-94 from four to six lanes between Lovers Lane and Sprinkle Road in Kalamazoo. The Portage Road interchange is being rebuilt with a single-point urban interchange, realigning Kilgore Road at Portage Road. The $87 million investment connects several I-94 expansion projects from west of US-131 to Sprinkle Road completed since 2008. A video explaining the project is available on MDOT's
YouTube channel.
County:
Kalamazoo
Highway:
I-94
Closest city:
Kalamazoo
Start date:
Saturday, April 9, 2022
Estimated end date:
Tuesday, Dec. 20, 2022
Traffic restrictions:
Two lanes of I-94 will be open in each direction.
Media Contact: