Traffic shift to eastbound I-94 lanes delayed
April 08, 2022
Contractors are anticipating shifting westbound I-94 traffic over to the eastbound lanes in early July to begin rebuilding the westbound lanes.
This is the second year of work on the two-year project to widen 2.7 miles of I-94 from four to six lanes between Lovers Lane and Sprinkle Road in Kalamazoo. The Portage Road interchange is being rebuilt with a single-point urban interchange, realigning Kilgore Road at Portage Road. The $87 million investment connects several I-94 expansion projects from west of US-131 to Sprinkle Road completed since 2008. A video explaining the project is available on MDOT's
YouTube channel.
County:
Kalamazoo
Highway:
I-94
Closest city:
Kalamazoo
Start date:
Thursday, April 21, 2022
Estimated end date:
Tuesday, Dec. 20, 2022
Traffic restrictions:
Two lanes of I-94 will be open in each direction.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 1,105 jobs.
Media Contact: