Project Information

Department Name Department of Corrections
Facility Name Jackson Complex
Project Name Lighting, Mechanical, Water/sewer, Building Energy Management (controls)
Completion Date July 2019
Project Cost $23,988,564
Savings (in $)

$1,570,710 Annually

Payback Period/ROI 15 years
Impact/Significance

Energy savings:

1,910,197 KWhrs electric

947,295    MCF gas

75,301      Kgal water/sewer

Project Summary

This work was completed as an energy performance contract. First an Investment Grade audit was completed. It was followed by implementing various energy conservation measures on 7 buildings defined in the audit.  The project was financed under an Energy Performance Contract which pays the cost of the investment through energy savings over a 15-year period.          

Additional Information Noresco Michigan Department of Corrections PDF