The web Browser you are currently using is unsupported, and some features of this site may not work as intended. Please update to a modern browser such as Chrome, Firefox or Edge to experience all features Michigan.gov has to offer.
Case No. U-22058, DTE Electric’s Application for Approval of Special Contracts with Google LLC
Introduction
On October 1, 2026, the Michigan Public Service Commission granted conditional approval of special contracts between DTE Electric and Google LLC for the provision of utility electric service to a Google data center. The Commission does not decide whether or where a data center can be built. Its authority applies only to the utility service needed to serve the facility, including the rates, terms, and conditions of that service.
The Michigan Public Service Commission’s role in this case is to review and approve, reject, or approve with conditions the contracts submitted by DTE Electric to serve the Google data center to be built in its service territory. In conducting its review, the Commission is charged with protecting the public interest and ensuring that the costs and risks associated with serving a large new electric customer are appropriately addressed.
The Commission’s Order puts protections in place, so other DTE customers are not responsible for costs and financial risks created by serving this large new load. The Commission will also continually monitor the costs being caused by the data center customer into the future and ensure customers will not bear any burden if projected affordability benefits do not materialize.
This issue brief explains the proposed special contracts, the Commission’s role, and the customer protections included in the Commission’s Order.
What did DTE Electric request?
On March 17, 2026, DTE Electric (DTE or the Company) filed an application with the Commission seeking approval of two special contracts between the Company and Google LLC (the Customer), which plans to build and operate a data center in Wayne County’s Van Buren Township. The two contracts (the special contracts) are a Primary Supply Agreement (PSA), which governs the terms and conditions of electric service provided to the Customer, and the Clean Capacity Accelerator Agreement (CCAA), which provides for new clean energy resources (primarily renewable energy and energy storage facilities) to be developed by the Company and paid for by the Customer. The Company requested the case be contested and also requested an expedited decision from the Commission.
What is the Commission’s authority related to the proposed data center?
Michigan law gives the Michigan Public Service Commission jurisdiction over the electric and natural gas rates charged by utilities to customers, including data centers, and the terms under which regulated utilities provide those services. When any new customer requests electric or natural gas service, the utility has a legal responsibility to provide it. The Commission is responsible for determining whether the proposed service and associated costs are reasonable and prudent and in the public interest.
The Commission may require specific terms and protections to ensure existing customers do not subsidize the costs of serving large load customers, including costs that could remain if a data center reduces its operations or leaves the utility system. The Michigan Public Service Commission has put in place some of the strongest ratepayer protections in the nation.
The Commission does not have authority over the siting or construction of data centers. It also does not issue construction or land-use permits or make decisions regarding water usage or whether a data center may be built. For this proposed data center, the Commission has the authority to review and approve, reject, or provide conditional approval of the special contracts between the utility and the data center customer.
What is a special contract?
A special contract is a negotiated agreement between a regulated utility and a customer that establishes rates, terms, or conditions for utility service that differ from those included in the utility’s standard rate book (Mich Admin Code 460.2012). In this case, a special contract is necessary to impose additional conditions on the customer to ensure that all costs caused by the large load customer are, in fact, paid for by that customer.
What are the terms of the proposed Primary Supply Agreement?
Under the proposed Primary Supply Agreement (PSA), the Customer would receive electric service under DTE's existing Commission-approved D11 Primary Supply Rate. This rate is generally available to large customers that contract for at least 50 Kilowatts of electric capacity and receive electricity at higher voltage levels.
The proposed PSA incudes terms beyond those normally required under the D11 rate including:
- A contract duration of 20 years (versus the normally required five years that would otherwise apply under the standard D11 Primary Service Rate).
- 80% minimum billing demand (versus 50 to 65% minimum billing demand that would otherwise apply under D11).
- A termination payment that ensures Google LLC will ultimately pay for at least 15 years of minimum monthly charges.
- Credit and collateral requirements that provide significant protection in the event the Customer ceases operations earlier than planned.
What is minimum billing demand?
Minimum billing demand (MBD) sets a minimum amount that a customer will pay each billing cycle regardless of actual use. In the proposed PSA in this case, it is 80% of the Customer’s contracted monthly electric demand. In other words, each month, the Customer will have to pay at least 80% of the contracted demand even if it doesn’t use any energy at all. If the actual demand is over 80%, the Customer will pay for its actual full demand and usage.
What are the terms of the Clean Capacity Accelerator Agreement (CCAA)?
Under the terms of the proposed CCAA, the Customer would pay for the development of up to 480 megawatts (MW) of energy storage facilities and up to 1,600 MW of renewable energy facilities. These facilities would be fully funded by Google LLC and owned and operated by DTE Electric. Google LLC will also give the utility 300 MW worth of capacity credits at no cost. The utility can use those credits to help demonstrate that it has enough power resources available to reliably serve customers, rather than having to obtain that capacity elsewhere. The CCAA also includes a termination payment as well as credit and collateral requirements, providing additional protection in the event the customer ceases operations earlier than planned.
Does DTE need a special contract to provide electric service to the Customer?
No. DTE could provide electric service to the Customer under its existing Commission-approved D11 Primary Supply Rate that does not provide these additional customer protections. However, the Commission Order requires provisions that enhance customer protections, including that the Customer must fully fund specific amounts of clean and renewable energy resources that the Customer would not otherwise have to pay for under the standard rate. Because these additional terms differ from DTE’s standard rate, they are included in special contracts that require Commission review and approval.
Why did DTE file this case if it's not required?
Although DTE could serve the Customer under its existing D11 Primary Supply Rate, the proposed special contracts include terms and conditions that are not part of that standard rate. Under Michigan rules, utilities must obtain Commission approval for special contracts that provide service in a manner or at a rate not covered by existing Commission–approved rates.
The proposed contracts also include provisions intended to protect other DTE customers from costs associated with serving this Customer. For example, the CCAA provides for the Customer to directly pay for a substantial amount of new clean energy resources. Without these additional provisions, some of the costs could otherwise be borne by other DTE customers.
What is the legal standard for approval of a special contract?
To approve a special contract, the Commission must find that approval is in the public interest.
What did the Commission find relative to the public interest in reviewing the special contracts?
The Commission found that approval of the special contracts serves the public interest, and “DTE Electric has demonstrated that approval of the special contracts will not increase rates, rate schedules, or the cost of service to other customers.” The Commission also found that the “terms and conditions of the PSA and CCAA reflect distinct protections for the utility with respect to stranded costs, mitigate cost subsidization for existing and future customers, and provide an opportunity for a benefit to customers in the form of electric rates that are lower than they otherwise would have been due to the increased share of fixed costs that will be borne by Google with the conditions described” in the order.
Did the Commission approve the special contracts?
The Commission provided conditional approval of the special contracts, specifying a list of conditions that DTE Electric must agree to for the approval to stand.
What conditions did the Commission include in its approval of the special contracts?
Several conditions were stipulated in the Commission’s approval of the special contracts, including:
- That the costs of serving Google LLC (including generation, transmission, distribution, or other costs) are not covered by other customers.
- DTE Electric commits to updating the operating parameters applicable to Google LLC when necessary to comply with MPSC, NERC, FERC, MISO, or ITC Transmission operational requirements.
- In the Company’s current Integrated Resource Plan application and Clean Energy Plan filing, the Company must provide a comparison of the resource requirements necessary to serve the Company’s load with and without the addition of Google LLC’s load and both with and without all large loads connected to DTE Electric’s system.
- There are no caps placed on the maximum costs Google LLC must pay for any necessary electric infrastructure upgrades.
- All revenue from any financial compensation mechanism earned in association with these contracts is treated as ordinary income to the benefit of all ratepayers. The financial compensation mechanism is added profits for the Company and recording it as ordinary income will allow the added profits to be passed on to ratepayers instead of retained by the Company.
- DTE Electric must work with Google LLC on compliance with Energy Waste Reduction requirements.
- DTE Electric must “file a cost allocation and rate design proposal that ensures that future large load interconnection customers pay the full costs associated with interconnection” in its next rate case.
- DTE must file an application for review of the status of the termination payments and collateral amounts within 3 years of load ramp completion. This occurs when the data center has reached full load.
- DTE must file updated interconnection procedures to allow customer-connected storage installations to export directly to the grid and to be used for both import and export as well as a draft tariff within 120 days of the Order.
As provided in the application, the special contracts include significant redactions. How could a thorough review of the contracts be conducted given these redactions?
All parties participating in the case had equal access to unredacted copies of all documents in the case. However, to protect commercially sensitive information, the case was governed by a protective order enforced by the presiding Administrative Law Judge (ALJ). So intervening parties had access to the full, unredacted record, but certain commercially sensitive information cannot be shared publicly. This is standard practice in Commission proceedings, and both the protective order and the ALJ ruling is part of the official record of the case and can be publicly accessed via the case docket.
Are there any next steps related to the Commission’s approval?
Yes. The Commission requires DTE Electric to file a letter within 30 days confirming that it accepts all conditions in the Order. If any special contract needs to be updated because of those conditions, DTE Electric must file the revised contract within the same 30‑day period in the docket.
Are there any protections in place to ensure that the expected benefits materialize and that customers remain protected over the duration of the special contracts?
Yes. The Commission will continue to oversee this matter. It may reopen the case at any time if the affordability benefits DTE Electric has claimed do not occur or disappear over time, or if any costs associated with serving Google LLC are in danger of being passed on to existing customers.