Case Summary
This case is Michigan's first solar siting certificate, and the first settlement, under Public Acts 233 and 234 of 2023 (U-21932). On June 18, 2025, Acceleration Solar filed an application with the Michigan Public Service Commission (MPSC) for a 90-megawatt (MW) solar project in Leslie Township, Onondaga Township, and Vevay Township in Ingham County. The Commission approved the settlement agreement on August 27, 2026, and the developer plans to begin construction in 2027.
The townships where the project would be located took part in the case, along with MPSC Staff. After reviewing the project and submitting testimony, the parties reached a settlement agreement and filed it for Commission consideration on July 31, 2026.
Why is this case before the MPSC?
Public Act 233 of 2023 (PA 233) created a state‑level siting process for large renewable energy facilities—solar, wind, and storage—in specific situations. A developer may apply to the MPSC for siting approval after complying with the requirements of Sections 223 and 224 of PA 233. However, the affected townships (also referred to as affected local units or ALUs) maintain local control over siting of such facilities if each ALU notifies the developer that it has a Compatible Renewable Energy Ordinance (CREO), which allows for the development of large renewable energy facilities, and unless any of the following occurs:
- An ALU requests Commission involvement.
- An ALU fails to timely approve or deny the project.
- An ALU denies a PA 233 Sec. 226(8)-compliant application.
- An ALU changes its ordinance while the project is pending to impose more restrictive requirements than PA 233 allows.
Developers must follow the MPSC’s Application Filing Instructions and Procedures (AFIP), approved in Case U-21547.
In this case, the ALUs did not each have a CREO, and the matter was therefore brought before the Commission. Ingham County—an ALU under PA 233 as clarified by the Court of Appeals—chose not to participate in the case and instead reached a separate host agreement (community benefits agreement) with Acceleration Solar.
For additional information on the PA 233 process, including what qualifies as a CREO, please visit the Commission’s Renewable Energy and Storage Facility Siting web page.
What does a settlement agreement mean in this type of case?
The settlement agreement means that all parties—Acceleration Solar, MPSC Staff, and the three townships—agree on project conditions that resolve all issues in the case and request Commission approval of a siting certificate.
What does the Commission consider when presented with a settlement agreement?
When a settlement agreement is filed, each party has fourteen days to file either agreement, objection, or statement of non-objection to the settlement (Administrative Hearing Rule 792.10431- Rule 431). Objecting parties are provided an opportunity to submit evidence and arguments in opposition to the settlement. In order to approve a proposed settlement agreement, the Commission must make the following findings:
- The public interest is adequately represented by the parties who entered into the settlement agreement.
- The settlement agreement is in the public interest and represents a fair and reasonable resolution of the proceeding.
- If any party objects to the settlement agreement (which then makes it a “contested settlement”), the Commission must also find that the settlement agreement is supported by “substantial evidence on the record as a whole.”
What would have happened if a settlement was not reached?
If the parties had not settled, the case would have proceeded to a full contested hearing, followed by a Commission order determining whether a siting certificate would be granted and under what conditions.