The web Browser you are currently using is unsupported, and some features of this site may not work as intended. Please update to a modern browser such as Chrome, Firefox or Edge to experience all features Michigan.gov has to offer.
PURPA
PURPA is a federal law enacted in 1978 in reaction to an energy crisis and implemented by state public service commissions for rate-regulated electric utilities. PURPA’s goals are to encourage competition, conservation, reliability and efficiency in generating and delivering electricity. One of the ways PURPA was set up to accomplish its goals was by establishing a new class of power generation facilities -known as qualifying facilities (QFs) -which would receive a special rate for selling their electricity back to the local electric utility and related regulatory treatment. PURPA imposed an obligation on local (“host”) utilities to purchase power from QFs in an effort to promote competition and achieve the other policy goals embodied in the federal law. Federal rules require state public service commissions and non-regulated utilities (primarily rural cooperatives and municipalities not regulated by state commissions) to set rates for the host utility to buy power from a QF. For an issue brief about PURPA, click here.
The Commission issued its second Report on the Implementation of the Public Utility Regulatory Policies Act of 1978 (PURPA) on April 20, 2020, as required by Section 6v of PA 341 of 2016. This report describes the status of qualifying facilities (QFs) in the state, the current status of power purchase agreements (PPAs) for each QF, and the Commission’s efforts to comply with the requirements of PURPA.
Staff Leads
Merideth Hadala
The Commission established separately docketed cases for all rate-regulated utilities and directed them to make avoided cost calculation filings in June 2016. The cases are proceeding and links to each docket are provided below.
- Alpena Power Company
- June 7, 2017 Settlement Agreement
- December 6, 2018 Settlement Agreement
- Consumers Energy Company
- May 31, 2017 Commission Order
- July 31, 2017 Commission Order
- November 21, 2017 Commission Order
- February 22, 2018 Commission Order
- October 5, 2018 Commission Order
- DTE Electric
- July 31, 2017 Commission Order
- December 20, 2018
- Indiana Michigan Power Company
- December 20, 2018
- March 21, 2019 Settlement Agreement
- Northern States Power
- December 20, 2018
- Upper Peninsula Power Company
- September 28, 2017
- January 23, 2018
- UMERC/Wisconsin Electric Power Company
- December 20, 2018
Related Dockets
The Commission issued an order in Docket U-20095 to address issues related to the avoided cost rates for capacity. Interested parties may file written or electronic comments on the determination of utility capacity requirements over a 10-year planning horizon and the criteria for evaluating a legally enforceable obligation. The final order was issued on October 5, 2018.
The Commission has ordered many utilities to include the biennial PURPA review in the Integrated Resource Plan (IRP) filing. Consumers Energy has updated PURPA avoided costs in its IRP Case No. U-20165. An Order on June 7, 2019, approves a contested settlement in this case.
Consumers Energy filed an Application for Approval of a Settlement Agreement to Resolve Rights and Obligations Under PURPA in Case No. U-20615.
PURPA TAC Reports
PURPA TAC Events
March 3, 2016
February 10, 2016
Agenda| MPSC Staff | PURPA Administrative Process
February 3, 2016
Agenda | Ken Rose | IPPC 1 | IPPC 2
January 13, 2016
Agenda | MPSC Staff | PURPA Implementation
December 8, 2015
Agenda | Elefant | MPSC Staff
PURPA Related Documents
PURPA Title II Compliance Manual
PURPA Contract List – Prepared by MPSC Staff