Altered Lifts
Alterations of an existing ski lift requires that an application and exhibits applicable to the alteration be submitted to the department. If the exhibits list calls for plans/drawings already on file with the department, provide a list of those for reference. Upon review and approval, a Phase One permit will be issued allowing foundations to be poured.
An inspection and additional exhibits must be submitted to the department to advance to Phase Two of the permit process allowing the machinery construction.
A final construction permit will be issued and load testing and final inspections scheduled upon submittal of exhibits required for Phase Three of the permit process.