Skip to main content

New Lifts

Before construction of a new lift, an application and relevant exhibits must be submitted to the department. Upon review and approval, a Phase One permit will be issued allowing foundations to be poured.

An inspection and additional exhibits must be submitted to the department to advance to Phase Two of the permit process allowing the machinery construction.

A final construction permit will be issued and load testing and final inspections scheduled upon submittal of exhibits required for Phase Three of the permit process.