Section 6.0, and its associated subsections, is limited to those designs for a PVMS that EGLE has contracted and is funded by public money or dollars. An owner/operator is not required to and should not include this section for a submittal to EGLE for official review. The information in this section is based on the State Occupation Code, Act 299, Article 20 Section 339.2011 which requires any public works in excess of $15,000 to be prepared, reviewed, and overseen by a licensed professional engineer (PE). However, 339.2012 exempts single family home construction of less than 3,500 square feet. Therefore, if the estimated cost of the installed PVMS (based on design, installation, and commissioning) is expected to be greater than $15,000 the additional information identified in this section must be provided.
6.1 PVMS design professional engineer and license number
6.2 Engineers estimated cost of the PVMS considering design, installation, and commissioning
In order for EGLE to complete its review the following information must be included in the identified subsections (even if it otherwise appears):
6.3 Design flow
6.4 Pipe sizing
6.5 Pipe layout schematic with any valving
6.6 Sampling locations
6.7 Failsafe devices
Information provided in Section 6.3 through 6.8 should be based on the Pre-Design Sub-Slab Testing that was completed in Section 2. Typically, EGLE will not contract for a presumptive mitigation system without a building and know or potential unacceptable exposures; however, if pre-design sub-slab testing cannot be completed due to a structure not being present, the submitter should contact EGLE regarding how to provide sufficient information to complete the requirements of this section. Each section identified above must provide the necessary supporting documentation, calculations, and figures as required to support the conclusions being drawn.