This section should identify the inspections that occurred and provide a discussion of the following:

  • Changes or modifications in use, operation, configuration, structural changes, or size of the structure.
  • Visual non-mechanical PVMS components such as labels for readability and presence, sealants, and building system.
  • Mechanical PVMS components for audible or visual indicators that a repair or replacement was necessary.

Other information that should be described in this section includes:

  • Location – where the inspection occurred.
  • Frequency – how often the inspection occurred.
  • Observations – what observations were made and noted.
  • Operation – that the PVMS continues to operate.
  • Response – what steps were taken if the visual inspection identified a response was necessary or warranted.

Key supporting information

  • Figure(s) – identifying the inspection point.
  • Table – identifying what was inspected and what information was document.
  • Inspection Form (optional) allowing the inspection to be performed in a standardize and routine approach, a record that the inspection(s) occurred, and that the system continues to function as designed.