M-227 resurfacing in Fredonia Township starts Tuesday
September 01, 2022
MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) will invest $302,400 to resurface 1.2 miles of M-227 from 15 1/2 Mile Road to 17 Mile Road in Leroy Township, south of Marshall.
County:
Calhoun
Highway:
M-227
Closest city:
Marshall
Start date:
Tuesday, Sept. 6, 2022
Estimated end date:
Monday, Oct. 31, 2022
Traffic restrictions:
There will be total closures of M-227 between 15 1/2 Mile Road and 17 Mile Road, as well as the ramps at I-69/M-227 (F Drive South) Exit 32 from Friday, Sept. 9, through Friday, Sept. 16.
There will be single-lane closures with traffic regulators for the rest of the project.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support nearly four jobs.
Safety benefit:
This work will improve the driving surface of the road and extend the life of the roadway.