I-96/Grand River Avenue interchange rebuilding project - Livingston County
About this project
The I-96/Grand River Avenue interchange project involves rebuilding the interchange as a diverging diamond interchange (DDI). As part of the project, three structures will be replaced along I-96: the Ore Creek culvert under I-96 and the two I-96 bridges over Grand River Avenue. The planned improvements to the interchange will require acquiring additional right of way.
Planned work
- Rebuild I-96 bridges over Grand River Avenue.
- Rebuild approximately 0.7 miles of I-96 approaches to accommodate bridge replacements.
- Rebuild and reconfigure ramps at the Grand River Avenue interchange as a DDI.
- Replace culvert under I-96.
Project stages & detours
-
2024 Construction
In fall 2024, MDOT will build temporary crossovers on the freeway.
-
2025 Construction
- Rebuild westbound I-96.
- Two lanes of eastbound and westbound I-96 traffic will be maintained on eastbound I-96.
- Stage 1 Design
- Close the Grand River Avenue ramp to westbound I-96. Detours are:
- Westbound Grand River Avenue to eastbound I-96, then Spencer Road to westbound I-96.
- Eastbound Grand River Avenue to the eastbound I-96 ramp, then Spencer Road to westbound I-96.
- Stage 1 Detour Graphic
- Rebuild westbound I-96.
-
2026 Construction
- Rebuild eastbound I-96.
- Two lanes of eastbound and westbound I-96 traffic will be maintained on westbound I-96.
- Rebuild the Grand River Avenue ramps in various stages. Primary detours are:
- Westbound Grand River Avenue to eastbound I-96, then Spencer Road to westbound I-96.
- Eastbound Grand River Avenue to Hilton Road, then Old US-23 to Spencer Road to westbound I-96.
- Stage 2 Detour Graphic
- For daily ramp closures, check Mi Drive.
- Rebuild eastbound I-96.