Skip to main content

US-41 nighttime paving in Harvey next week

MARQUETTE, Mich. – Nighttime paving work will begin next week at the Michigan Department of Transportation (MDOT) resurfacing project on US-41 From Big Creek Road to the M-28 intersection in Marquette County. 

Crews plan to pave the US-41/M-28 intersection in Harvey at night to minimize traffic impacts. Paving is scheduled for Monday through Thursday nights, June 20-23, from 7 p.m. to 7 a.m. each night. If necessary, paving work may continue Friday night, June 24.

Motorists should expect single-lane closures using traffic regulators.

The work is part of MDOT’s $3 million investment to resurface 3 miles of highway. The project includes milling and multiple-course asphalt resurfacing, joint repairs, intersection improvements, carpool parking lot resurfacing, guardrail replacement, signal upgrades, and pavement markings. 

Work started May 16 and is expected to be completed on Sept. 2.

Media Contact: