M-18 resurfacing project starts April 15 in Gladwin County

MT. PLEASANT, Mich. - The Michigan Department of Transportation (MDOT) is investing approximately $4.1 million to improve 17.6 miles of M-18 in Gladwin County from First Street north to the Gladwin/Roscommon county line. Work includes resurfacing, sidewalk ramps, shoulder gravel, pavement markings, and slope restoration, as well as drainage upgrades at the Meridith Grade Road intersection.

County:
Gladwin

Highway:
M-18

Closest cities:
Gladwin

Start date:
Monday, April 15, 2024

Estimated end date:
May 2024

Traffic restrictions:
Traffic will be maintained using traffic regulators.

Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 50 jobs.

Safety benefit:
This work will improve the driving surface of the road and extend its service life.

 