Be aware of fake MDOT texts demanding toll or traffic ticket payments. MDOT does not operate any toll roads. Contact the Michigan Attorney General for information on how to identify scams and file a complaint.
KL Avenue rebuilding starts this week to complete US-131 bridge project
March 11, 2026
Fast facts:
- Work resumes this week for the final year of the three-year, $24 million investment to replace the US-131 bridges over KL Avenue and the Amtrak railroad in Kalamazoo.
- The primary work this year will be rebuilding KL Avenue under US-131.
- Crews will be completing median and slope restoration on US-131 around the two new bridges.
KALAMAZOO, Mich. - The Michigan Department of Transportation (MDOT) and contractor Davis Construction Inc. are starting work this week to rebuild KL Avenue under US-131 in Oshtemo Township. This is the final year of the three-year, $24 million investment to replace the US-131 bridges over KL Avenue and the Amtrak railroad in Kalamazoo County.
Work this year will involve rebuilding KL Avenue under US-131, including building retaining walls and a shared-use path along KL Avenue.
Drivers can expect intermittent, short-duration single-lane closures on US-131 as crews complete median and slope restoration around the new bridges.
KL Avenue will remain closed and detoured throughout the project. Completion is expected in mid-June.
Media Contact: