Resurfacing starts on M-60, M-86 and M-99 in Calhoun and St. Joseph counties April 13
April 07, 2026
MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) and contractor Lakeland Asphalt Corp. will be repaving 5.5 miles of three state highways and one carpool lot:
- 1.1 miles of M-86 from Nottawa Street to Shimmel Road in Centreville.
- 3.6 miles of M-60 from Glendale Avenue to Main Street in Burlington.
- 0.8 miles of M-99 from Powers Street to M-60 (Leigh Street) in Homer.
- The Tekonsha carpool lot.
This $1.7 million investment includes milling and asphalt overlay, new pavement markings, and sidewalk ramp upgrades compliant with the Americans with Disabilities Act of 1990.
Counties:
Calhoun and St. Joseph
Highways:
M-60, M-86 and M-99
Closest communities:
Burlington, Centreville, Homer and Tekonsha
Start date:
Monday, April 13, 2026
Estimated end date:
Friday, July 17, 2026
Traffic restrictions:
Single-lane closures.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 14 jobs.
Safety benefit:
The new pavement and pavement markings will improve the ride quality and better lane visibility for drivers. The sidewalk ramp upgrades will improve accessibility for pedestrians.
Media Contact: