The web Browser you are currently using is unsupported, and some features of this site may not work as intended. Please update to a modern browser such as Chrome, Firefox or Edge to experience all features Michigan.gov has to offer.
M-66 and M-37 resurfacing starts Aug. 3 in Battle Creek
July 28, 2026
MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) and contractor Pavement Maintenance Systems will be resurfacing M-66 from Beckley Road/B Drive North to S Drive South and M-37/I-94 Business Loop from I-94 to Helmer Road.
The $1.4 million investment includes 10.4 miles of micro-texture pavement milling, over band crack filling, single-course chip seal and fog seal.
Counties:
Calhoun
Highway:
M-66
Closest communities:
Battle Creek, Athens
Start date:
Monday, August 3, 2026
Estimated end date:
Tuesday, September 15, 2026
Traffic restrictions:
Single- and double-lane closures.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 12 jobs.
Safety benefit:
Lane closures during this type of work are necessary to provide the safest work area possible for crews and motorists. These improvements will provide drivers with a safer, smoother ride and extend the life of the road.