Changes coming Friday to M-14/I-96 rebuilding project in Plymouth Township, Livonia
September 16, 2026
Fast facts:
- Traffic on westbound I-96 will be switched over to the rebuilt westbound lanes from Levan Road to I-275.
- Additional ramps at the I-275 interchange will open.
- To prepare for the traffic switch, short-term lane and ramp closures will be required.
LIVONIA, Mich. - The ongoing rebuilding of the I-96/M-14 interchange in western Wayne County is expected to reach a significant milestone Friday, Sept. 18, when westbound I-96 traffic from Levan Road to I-275 will be switched over to the rebuilt westbound lanes. Currently, both directions of I-96 are sharing the eastbound side of the freeway with two lanes open in each direction.
Beginning at 5 a.m. and ending by 7 p.m. Friday, westbound I-96/M-14 will have one lane open from Wayne to Sheldon roads.
Beginning at 9 a.m. and ending by 3 p.m. Friday, the following closures will be in place to prepare for the traffic shift:
- The eastbound M-14 ramp to northbound I-275 will close.
- The westbound I-96 ramp to northbound I-275 will close.
- Northbound I-275 will have one lane open from Ann Arbor Road to 5 Mile Road.
By sunset on Friday the following changes will be in place:
- Westbound I-96 traffic will be in its normal configuration from Levan Road to I-275. Only the left lane will remain closed.
- The Newburgh Road entrance ramp to westbound I-96 will open.
- The westbound I-96 ramp to northbound I-275 will have both lanes open.
- The westbound I-96 ramp to southbound I-275 will open.