Marshall Modernization Project pausing for winter
November 16, 2026
Fast facts:
- Work on the Marshall Modernization Project is set to pause for the winter this week; construction will resume in the spring.
- In 2027, work will include rebuilding eastbound I-94, rebuilding M-311 (11 Mile Road) over I-94, and completing the I-94 interchange with M-311 and M-96 (Michigan Avenue).
- This was the second year of a three-year, $335 million investment to rebuild and repave I-94, I-69 and M-96 in support of the Marshall Area Jobs, Opportunity and Recreation (MAJOR) Campus.
MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) is pausing work the week of Nov. 16 on the Marshall Modernization Project in support of the Marshall Area Jobs, Opportunity and Recreation (MAJOR) Campus.
Until work resumes in the spring, there will be one lane open in each direction on M-96 (Michigan Avenue) and M-311 (11 Mile Road). There will be two lanes open in each direction of I-94, and all ramps at Exit 104 will be open.
2026 was the second year of this three-year, $335 million investment. Work accomplished this year includes:
- Rebuilding westbound I-94 between the Kalamazoo River and M-96 Exit 104,
- Rebuilding the M-96/I-94 Business Loop (BL) (Michigan Avenue) bridge over I-94,
- Rebuilding the eastbound and westbound I-94 Exit 104 ramps,
- Realigning the M-311 ramp to westbound I-94,
- Installing three box culverts, and
- Realigning Dickinson Creek.
Work in 2027 is expected to start in March with the demolition of the M-311 bridge over I-94 to start bridge reconstruction. Other work in 2027 will include rebuilding eastbound I-94 and eastbound ramps at Exit 104, completing the M-96 boulevard conversion, and rebuilding the Pigeon Creek box culvert under M-96.