BVM application decision
Typically, MDOT will notify an applicant of its decision within ninety (90) days of receiving a complete BVM Permit application.
MDOT may take one of the following actions:
- Approve the application
- Approve the application with limitations and/or modifications, or
- Deny the application
Upon receiving notice of MDOT's decision to approve an application (with or without limitations and/or modifications), the applicant has thirty (30) days to submit the following items:
- Payment of the $500 BVM Permit fee
- Payment of any additional review or inspection fees, if MDOT determines they are necessary
- Payment of the value of the vegetation approved for removal or trimming, as determined by MDOT
- A $5,000 electronic individual performance bond for the work to be completed under the BVM Permit
- If the applicant prefers one bond to cover multiple BVM Permits, a $50,000 electronic blanket performance bond may be submitted instead
- An electronic certificate of insurance for work covered under the BVM Permit
- If MDOT approves the application with limitations and/or modifications, the applicant must submit the following items incorporating the limitations and/or modifications, if applicable:
- Revised lists of the trees and shrubs to be removed or trimmed
- A revised full-color photographic aerial map
- A list of all required mitigation with any applicable conditions
- A list of all additional required conditions
A failure to submit the required items within thirty (30) days of receiving notice of MDOT's decision will result in the cancellation of the application's approval.
An applicant may pay a $150 fee to extend this deadline an additional 30 days.