I-94 resurfacing starts Monday between New Buffalo and Sawyer
July 05, 2022
COLOMA, Mich. - The Michigan Department of Transportation will be investing $5.9 million to resurface 5.4 miles of I-94 between Kruger Road and Three Oaks Road. Work includes milling and asphalt resurfacing, shoulder corrugations, and new pavement markings.
County:
Berrien
Highway:
I-94
Closest cities:
New Buffalo and Sawyer
Start date:
Monday, July 11, 2022
Estimated end date:
Friday, Oct. 21, 2022
Traffic restrictions:
Lane closures and traffic shifts.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support nearly 75 jobs.
Safety benefit:
This work will repair and preserve the pavement, extending the life of the roadway and providing a safer and smoother driving surface.