US-2 resurfacing project in Manistique starts Aug. 29
August 25, 2022
MANISTIQUE, Mich. - The Michigan Department of Transportation (MDOT) is investing about $555,000 to resurface 0.8 miles of US-2 from west of Chippewa Avenue to the Manistique River bridge in the city of Manistique in Schoolcraft County. Work includes resurfacing, aggregate shoulders, and pavement markings.
County:
Schoolcraft
Highway:
US-2
Closest city:
Manistique
Start date:
Monday, Aug. 29, 2022
Estimated end date:
Friday, Sept. 30, 2022
Traffic restrictions:
Motorists should expect lane closures with traffic regulators. A lane width restriction of 12 feet will be in place during the project.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support seven jobs.
Safety benefit:
This work will extend the lifespan of the roadway and result in a smoother driving surface and increased safety for motorists.Media Contact: