M-57 bridge repairs over the Flint River start June 12

BAY CITY, Mich. - The Michigan Department of Transportation (MDOT) will invest $1.9 million in critical bridge repairs on M-57 over the Flint River in Genesee County. Work includes pavement repairs to the bridge deck and approaching pavement, beam repairs, guardrail, placing additional rip rap, and epoxy seal coating.

County:
Genesee

Highway:
M-57

Closest city:
Montrose

Start date:
Monday, June 12, 2023

Estimated project end date:
August 2023

Traffic restrictions:
This work will require lane closures and traffic shifts via a temporary signal. Work on the signal may begin as early as June 1 to stage the project site prior to bridge work. Signal work will require intermittent lane impacts, with nearly all work occurring from the shoulder of M-57.

Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support nearly 23 jobs.

Safety benefit:
This project is intended to improve the condition of the M-57 bridge, extending the life of the structure.