The web Browser you are currently using is unsupported, and some features of this site may not work as intended. Please update to a modern browser such as Chrome, Firefox or Edge to experience all features Michigan.gov has to offer.
I-94 repaving starts Monday between Coloma and Hartford
June 15, 2023
COLOMA, Mich. - The Michigan Department of Transportation (MDOT) will invest $484,000 to resurface portions of eastbound and westbound I-94 between Coloma, Berrien County, and Hartford, Van Buren County. Planned work includes paving, guardrail replacement, and new pavement markings.
Counties:
Berrien and Van Buren
Highway:
I-94
Closest cities:
Coloma, Watervliet, and Hartford
Start date:
Monday, June 19, 2023
Estimated end date:
Monday, June 26, 2023
Traffic restrictions:
Drivers should expect nightly single-lane closures from 7 p.m. to 7 a.m.
Safety benefit:
This work will improve the driving surface of the road and extend the life of the roadway.
Media Contact: