MDOT open house for I-94 repaving and bridge project in Battle Creek

MARSHALL, Mich. - The Michigan Department of Transportation (MDOT) invites the public to attend an open house to discuss a planned 2023 project to repave I-94 between Helmer Road and 17 1/2 Mile Road and rebuild or repair 17 bridges in Battle Creek, Emmett Township, and Marshall Township.

Who:
Community stakeholders
Calhoun County representatives
City of Battle Creek representatives
Local businesses
Interested residents
MDOT staff and contractors

When:
Monday, March 20, 2023
4-6 p.m.

Where:
Battle Creek Public Works
Multi-Purpose Room 214
150 S. Kendall St.
Battle Creek, MI 49015

Accessibility:
Accommodations can be made for persons who require mobility, visual, hearing, written, or other assistance for participation. Large print materials, auxiliary aids or the services of interpreters, signers, or readers are available upon request. Please contact Orlando Curry at 517-241-7462 or complete Form 2658 for American Sign Language (ASL) located on the Title VI webpage: https://www.Michigan.gov/MDOT/Programs/Title-VI. Requests should be made at least five days prior to the meeting date. Reasonable efforts will be made to provide the requested accommodation or an effective alternative, but accommodations may not be guaranteed.

Project information:
The three-year, $160 million investment includes repaving 10 miles of I-94 between Helmer Road and 17 1/2 Mile Road, rebuilding nine bridges, and repairing eight others. Repaving work is planned from west of Helmer Road to 6 1/2 Mile Road, and from M-96 (Michigan Avenue) to 17 1/2 Mile Road.

The I-94 bridges planned for rebuilding are at Capital Avenue, 6 1/2 Mile Road, M-294 (Beadle Lake Road), 9 Mile Road, and the Kalamazoo River. Bridges with planned repairs are at Riverside Drive, I-194, F Drive South, M-96 (Michigan Avenue), M-311 (11 Mile Road) and 17 Mile Road (Old US-27).

Work is anticipated to begin in April 2023 and be completed by in early 2025.

Work planned for 2023 includes bridge work at Capital Avenue and the westbound I-94 bridges over 6 1/2 Mile Road, M-294 (Beadle Lake Road), 9 Mile Road and the Kalamazoo River. I-94 repaving work is planned from west of Helmer Road to Riverside Drive, and from M-311 (11 Mile Road) to the I-69 interchange.

2024 work includes bridge work on eastbound I-94 over 6 1/2 Mile Road, M-294 (Beadle Lake Road), 9 Mile Road and the Kalamazoo River. I-94 repaving work is planned from Riverside Drive to 6 1/2 Mile Road, and from M-96 (Michigan Avenue) to M-311 (11 Mile Road), and from the I-69 interchange to 17 1/2 Mile Road.

2025 work is repaving at the Battle Creek Rest Area on eastbound I-94.