US-23 Flex Route Phase 2 update: Multiple US-23 lane, ramp closures begin Thursday in Livingston County

LANSING, Mich. - As part of truss/sign installation beginning Thursday for the US-23 Flex Route project in the Brighton area, the following closures will occur on Thursday, May 16:

This work is part of the Michigan Department of Transportation's (MDOT) ongoing $162 million investment to extend the US-23 Flex Route from north of 8 Mile Road to I-96. The project consists of less than 7.5 miles of hot-mix asphalt rebuilding and improvements, shoulder widening, interchange reconfigurations, bridge replacement, and improvements at nine structures. The US-23 Flex Route Phase 2 extension focuses on traffic safety, operations, infrastructure condition, and the directional peak period congestion along the US-23 corridor.   

MDOT built the first Flex Route on US-23 between M-14 and 8 Mile Road in 2016 and 2017. That work involved installing an active traffic management (ATM) lane with other safety improvements, as well as operational improvements and addressing condition needs. 

Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improve the condition of the state's infrastructure.

County:
Livingston

Highway:
US-23

Closest city:
Brighton

Start date:
Thursday, May 16, 2024

Completion date:
Friday, May 24, 2024

Overall project completion date:
January 2026

Traffic restrictions:
Northbound US-23 will be closed intermittently at Grand River Avenue from 11 p.m. Thursday, May 16, to 5 a.m. Friday, May 17.

Southbound US-23 will be closed intermittently from Spencer Road to I-96 from 11 p.m. Wednesday, May 22, to 5 a.m. Friday, May 24.

The northbound US-23 ramp to eastbound I-96 will be closed from 9 p.m. Thursday, May 16, to 5 a.m. Friday, May 17. Traffic will be detoured via westbound I-96 and Spencer Road to eastbound I-96.

The southbound US-23 ramp to westbound I-96 will be closed from 9 p.m. Wednesday, May 22, to 5 a.m. Thursday, May 23. Traffic will be detoured via eastbound I-96 and Kensington Road to westbound I-96.

The eastbound I-96 ramp to southbound US-23 will be closed from 9 p.m. Thursday, May 23, to 5 a.m. Friday, May 24. Traffic will be detoured via Kensington Road and westbound I-96 to southbound US-23.

Motorists are advised to seek alternate routes.

Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 1,839 jobs.

Safety benefit:
These improvements will provide increased safety and mobility in this area of US-23, which is a significant state, national, and international trade corridor.