M-553 Marquette resurfacing project starts May 20

MARQUETTE, Mich. - The Michigan Department of Transportation (MDOT) is investing about $1 million to mill and resurface about 2 miles of M-553 between Division Street and US-41 in Marquette. Work will include asphalt milling and paving, sidewalk ramps, curb and gutter, and pavement markings.

County:
Marquette

Highway:
M-553

Closest city:
Marquette

Start date:
Monday, May 20, 2024

Estimated end date:
August 2024

Traffic restrictions:
Motorists should expect single-lane closures.

Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 12 jobs.

Safety benefit:
This work will improve the safety and operations of the roadway and provide a smoother driving surface, extending the life of the road.