M-14/I-96 project update: Lane and ramp closures this weekend through mid-December
October 31, 2025
Fast facts:
- The M-14/I-96 project in Wayne County is wrapping up for 2025.
- Various lane and ramp restrictions will be in place Nov. 2 - late December.
- Work to rebuild the westbound lanes will begin in February and continue to the end of 2026.
LIVONIA/PLYMOUTH TOWNSHIP, Mich. - The M-14/I-96 project between Beck Road and Newburgh Road moves to the wrap-up phase for 2025. Beginning Sunday, Nov. 2, crews will be closing lanes and ramps to reconfigure pavement markings and move barrier wall in preparation of opening the newly rebuilt eastbound side of M-14/I-96.
5 a.m. - 6 p.m. Sunday, Nov. 2:
• The Beck Road entrance ramps to eastbound M-14 will be closed.
• Eastbound M-14 Exit 20 to Sheldon Road will be closed.
7 a.m. - 7 p.m. Tuesday, Nov. 4:
• The northbound and southbound I-275 ramps to eastbound I-96 will be closed.
• Eastbound I-96 Exit 173 to Newburgh Road will be closed.
7 a.m. - 7 p.m. Wednesday, Nov. 5 - Monday, Nov. 10:
Crews will be moving barrier wall and patching.
• Eastbound M-14/I-96 traffic will be shifted onto the newly rebuilt eastbound side with one lane open.
• Westbound I-96/M-14 will have one lane open from Newburgh Road to Sheldon Road 7 a.m. - 7 p.m. daily, then two lanes overnight.
• All entrance and exit ramps to and from eastbound M-14/I-96 will be open, except the Sheldon Road entrance ramp.
7 a.m. - 7 p.m. Saturday, Nov. 8 - Sunday Nov. 9 (and the following weekend, depending on weather):
Crews will perform patching on the westbound side before reopening for winter.
• The Newburgh Road entrance ramp to westbound M-14/I-96 will be closed.
• The westbound I-96 ramp to northbound I-275 will have one lane open.
• The southbound I-275 ramp to westbound M-14 will be closed.
Late Monday, Nov. 10:
• Eastbound and westbound M-14/I-96 will reopen to two lanes between Beck Road and Newburgh Road until mid-December.
• The Sheldon Road entrance ramp to eastbound M-14 will reopen.
Between Nov. 10 and mid-December, crews will be working on barrier wall, drainage and the shoulders before reopening the freeway to three lanes in each direction, along with reopening all ramps.
In February, crews are expected to return to begin rebuilding the westbound lanes, along with work on the I-275 interchange, through late 2026. The freeway will have two lanes open in each direction.
All this work is part of an overall $140 million investment to rebuild M-14/I-96 in the city of Livonia and Plymouth Township, Wayne County. The Metro Trail will be rebuilt during the 2026 season. Project details and maps can be found at www.M14Reconstruction.org.
Based on economic modeling, this investment is expected to directly and indirectly support 1,336 jobs.Media Contact: