Westbound I-94 traffic shift in Jackson begins Monday

LANSING, Mich. - The Michigan Department of Transportation (MDOT) will shift westbound I-94 between M-106 (Cooper Street) and US-127 Monday.

This work is part of MDOT's ongoing $120 million investment to rebuild and widen I-94 near the Airport Road interchange to just west of the east US-127/I-94 interchange in Blackman and Leoni Township. The I-94 project involves upgrading the US-127/M-50 (West Avenue)/I-94 interchange to a diverging diamond interchange, the Elm Road interchange with roundabouts, and the Lansing Avenue bridge over I-94.

Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improve the condition of the state's infrastructure.

County:
Jackson

Highways:
I-94
US-127
M-106 (Cooper Street)
Elm Road

Closest city:
Jackson

Start date:
9 a.m.
Monday, June 12, 2023

Completion date:
3 p.m.
Monday, June 12, 2023

Overall I-94 project completion date:
November 2023

Traffic restrictions:
This project will require a single-lane closure on westbound I-94 while the traffic shift is in process.

Northbound US-127 traffic heading for to westbound I-94 will be detoured via eastbound I-94 to the Sargent Road interchange to enter westbound I-94.

Motorists are advised to seek alternate routes.

Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 1,524 jobs.

Safety benefit:
This project will increase safety for workers and motorists through this work zone.