Southbound I-475 closed at Flint River Oct. 26 - Nov. 1 in Flint for beam setting
October 21, 2024
DAVISON, Mich. - The Michigan Department of Transportation (MDOT) is closing southbound I-475 at the Flint River starting Oct. 26 for beam setting. This work is part of a $141 million investment to rebuild more than 3 miles of I-475 from the Flint River to Carpenter Road in Flint.
Funding for this project is made possible by Gov. Gretchen Whitmer's Rebuilding Michigan program to rebuild the state highways and bridges that are critical to the state's economy and carry the most traffic. The investment strategy is aimed at fixes that result in longer useful lives and improves the condition of the state's infrastructure.
County:
Genesee
Highway:
I-475
Closest city:
Flint
Start date:
Saturday, Oct. 26, 2024
Estimated end date:
Friday, Nov. 1, 2024
Overall project end date:
December 2025
Traffic restrictions:
Southbound traffic will be detoured via Stewart Road Exit 9, westbound Stewart Road, southbound James P Cole Boulevard, eastbound Hamilton Avenue, and eastbound Davison Road back to I-475. Northbound I-475 is currently closed to traffic during the ongoing rebuilding project.
Jobs numbers:
Based on economic modeling, this investment is expected to directly and indirectly support 1,706 jobs.
Safety benefit:
This project will enhance mobility and increase safety along the I-475 corridor. The southbound I-475 closure is necessary to provide the safest work area possible for crews and motorists while beam-setting work is performed on northbound I-475 over the Flint River.